The Lodge – Blog 4 – Eco Joists and MVHR

March 8, 2024

With the timber frame erected, the team fit the eco-joists for the roof and began installing the MVHR system.

Timber Frame Erection

Eco-joists are engineered timber components with V-shaped steel webs that enable quick and easy installation of services and utilities.

Timber Construction

The mechanical ventilation and heat recovery (MVHR) system could then be fitted within the pipes and ducting threaded through the joists.

Timber Frame Structure

A mechanical ventilation system is a necessary feature of an airtight timber frame home.

MVHR Installation

Thermal efficiency prevents heat from escaping the building and cold air from outside entering the property, but with ventilation vital for a healthy indoor environment, it’s essential that air circulation is incorporated into the design.

Mechanical Ventilation and Heat Recovery

Replacing stale air, humidity, condensation, and pollutants from inside with a supply of fresh filtered air into the home ensures clean air quality at all times.

MVHR System

The MVHR system comprises an air-handling unit, which can be installed in an attic space, plant or utility room, and ducting. The unit recovers heat from the outgoing stale air and transfers it to the incoming fresh air, delivering low-cost warmth throughout the property, an added benefit of the system.

Timber Frame Bungalow

Our new bungalow’s MVHR system has been designed and supplied by Systemair a company that provides quality heating, ventilation and air conditioning products that have been used in many Scandia self build projects.

More posts:

As work continues at pace on this bespoke timber frame home, another exciting milestone has been reached with the installation

Construction continues to move forward with the installation of plasterboard. Following the successful completion of the first fix plumbing, carpentry,

The exterior envelope of the timber frame structure has been completed, with a combination of render, natural stone and composite

Another important stage in the construction process was completed with the installation of the underfloor heating system and the pouring

With the structural shell of the new bungalow complete, work moved swiftly onto the first fix stage and fitting of

Why not visit our self build show village in the heart of West Sussex

Scandia-Hus Open Day Event

Join us on Saturday 17th October for the Scandia-Hus Open Day at our Self Build Show Centre in Sussex.