Simply click on an image to see the various stages or
scroll down for more information.
Scandia Hus logo


Build Diary step by step







Work began at the end of 2006 on this project. Our customer wanted a new home and, as he loved the area he lived in, decided to build his new new home in place of his existing one. The first thing we had to do was demolish the existing dwelling. The area was cleared creating a base on which to build his dream home. Step 1 footage was filmed mid December 2006.
Click here to see Step 1 footage


The beginning of 2007, and work began on building the new house. The scaffolding was erected and care was taken to protect the landscape which will remain with the new build. The first kit was delivered with rigid insulation and breather paper pre-fitted at the factory. The external panels and steel supports were craned into the site. Erection of the internal studs began in preparation for the partitions. Step 2 footage was filmed at the beginning of January.

Click here to see Step 2 footage


Mid January 2007, and work has already progressed to the next floors. The steel and attic trusses were craned into position to provide further accommodation on the 2nd floor, within the roof space. Erection of further internal load bearing stud walls continues. Step 3 footage was filmed in the middle of January.
Click here to see Step 3 footage

Early February 2007 and work continues at a rapid pace. All external and internal load bearing walls are erected and braced. The first and top floor panels are in place. Step 4 footage was filmed at the beginning of February.
Click here to see Step 4 footage

Late February 2007 - all windows have been fitted and the roof cross batons are in place. Care continues to be taken to protect the trees, all of which have preservation orders. Internal works continue apace. Step 5 footage was filmed at the end of February.
Click here to see Step 5 footage

Mid March 2007 - externally, the roof tiles are being laid. Internally, the electrics have had their first fix and the plasterboard is being fixed. Step 6 footage was filmed in the middle of March.
Click here to see Step 6 footage

Mid April 2007 - externally, the roof tiling is now complete. Internally, the downlighters to the ground floor have been fire-proofed, the first fix carpentry on the first and second floors is complete and the first fix plumbing is complete.Step 7 footage was filmed in the middle of April.
Click here to see Step 7 footage

Mid May 2007 - the cabling has been put in place for the audio visual system, which will be used throughout the house. The underfloor heating has been installed. Insulation continues apace and the internal carpentry is near to completion. The link from the garage to the house, via the utility area, is almost complete. Step 8 footage was filmed in the middle of May.
Click here to see Step 8 footage

During the Summer months, work continued apace both internally and externally. The internal carpentry is now complete. Filming took place in mid Summer for Step 9 and late Summer for Step 10.
Click here to see Step 9 footage

Click here to see Step 10 footage

Early Autumn 2007 - efforts are now being concentrated on the internal aspects of the build. The kitchen has been fitted and work on the interior continues apace in preparation for completion of the project.
Click here to see Step 11 footage

November 2007 - all external works are now complete. The total in-house electrical system has been installed and the bathrooms are in place with the bathrooms tiled. The staircase is in place and the wrought iron balustrades and oak handrails are soon to be delivered.
Click here to see Step 12 footage

January 2008 - work continues on the finishing touches for the interior and landscaping has begun on the rear garden, with the turfing and patio area being completed.
Click here to see Step 13 footage

Spring 2008 -
Click here to see Step 14 footage