Week 12: Traditional Tudor Style House Photo Diary

The decorator has applied the second coat of wood stain to the barge boards and soffits.  The first coat was applied before they were fitted.image16-11-07_08-26-37-29small

The bricklayers have made good progress with the blockwork and are now working on the gable ends.image16-11-08_16-06-37-30small

The brick soldier course has been completed above the ground floor windows and rear patio doors.
image16-11-10_11-21-37-29small

image16-11-10_15-36-37-33small

Work continues at a pace inside.  First fix plumbing and electrics is complete, and plasterboard is being fitted to the ground floor ceilings.image16-11-12_08-31-37-30small

 